The slab runs short of concrete
Ordering
Cause
A deeper excavation, a thickened edge or a soft base takes more concrete than the calculation allowed.
Why it matters
If the last section waits too long, a cold joint forms that weakens the slab.
Our solution
We work out the volume from your measurements before we batch, and on stepped jobs we calculate each level separately.
Prevention / next step
Measure the depth at several points and send us every section on its own.
Signs to watch for:
- Formwork filling slower than expected
- Several levels or steps